- Community Engagement Sessions
- Previous Community Engagement Sessions
- Frequently Asked Questions
- General Questions
- Flood Mitigation Impacts on Land Use
- Land Acquisition
- Berm Questions
- Tree Removal
- Ground Seepage
- Vibration Monitoring
- Downtown
- Lehigh
- Urban Tree Strategy
- Memorial Benches
- Monetary Questions
- Centennial Park
- Midland
- Willow Estates
- Traffic Impact Assessment (TIA)
- North Drumheller (Michichi Creek & Grove Plaza)
- Newcastle
- Glossary of Terms
- Nacmine Berm
- Resources
- Glossary of Terms
- Flood Mitigation Project Schedule
When the berms are built in various neighborhoods, is it the Town's intention to have a drainage ditch between the properties and berms so that there is system in place for heavy rains and protection of the houses?
Yes. The berm designs will include the design of an overland conveyance route along the inside toe of the berms.
When the berms are being constructed and heavy compaction is carried out, who will be covering the damages to house foundations and cracked wallboard that may occur?
There will be provisions in the contract documents requiring contractors to undertake the work in a manner to mitigate impacts to adjacent structures in their use of heavy equipment.
In the past, mine shafts that run under the river and throughout the Drumheller valley have been inundated by flood / storm water, what is being done to protect residential properties, i.e. from underground flooding?
Mine shafts are outside the scope of the current flood mitigation program.
What measures are in place for protection of the greenbelt, in particular, the natural native poplar trees?
Unfortunately, some trees will need to be removed to facilitate construction. Tree inventories and assessment are completed during design and a 5:1 tree replacement strategy is being implemented.
As the current berms in Drumheller do not meet the design flood elevation of 1850 m3/s plus 0.5m freeboard, if someone intends to take out a development permit do they have to build the main floor to 1850 m3/s plus 0.5 m freeboard?
Residents located within the flood hazard overlay in the Land Use Bylaw must construct the first floor of their houses to the flood construction level which is the water elevation of an 1850 m3/s flow rate on the Red Deer River. Residents are not required to include a freeboard, however, building above the flood construction level increases their resilience to future flood events. The flood construction level for protected areas will be re-evaluated in the Land Use Bylaws once the berms are built.
In regard to the "protected flood fringe" area and when does the Town intend to address this concept in the Town's Land Use Bylaw so that realtors and property owners have knowledge of future regulations?
The current Municipal Development Plan, issued in December 2020, refers to the new Provincial 100-year regulatory design flow rate of 1850m3/s. Of the 23 times the design flow rate is mentioned, there are 2 occurrences where the old, outdated flow rate inadvertently did not get updated. The Town is aware of this and plans to update the MDP for this and a few other typographical errors in spring 2022.
When will the Town address the conflicting information in the Municipal Development Plan with regards to building berms to 1640 m3/s plus 0.75 m freeboard and 1850 m3/s plus 0.75 m freeboard?
The current Municipal Development Plan, issued in December 2020, refers to the new Provincial 100-year regulatory design flow rate of 1850m3/s. There is no reference to the outdated design flow rate of 1640 m3/s.