Latest updates on the Drumheller Resiliency & Flood Mitigation Project will be posted on this page. Once the updates are no longer considered new, the information will be stored on one of the Be Informed pages.
If you have any questions, email floodreadiness@drumheller.ca or contact the Drumheller Resiliency & Flood Mitigation Office directly here.
January 16, 2023: Aquatic Assessment Completed for Michichi Creek Berms
CGI has completed an aquatic assessment of Michichi Creek, a necessary step in the construction of two berms in the area. The assessment covered the land that will be occupied by the North Drumheller Michichi Creek West Berm and the North Drumheller Michichi Creek East Berm projects.
Kerr Wood Ledial is the firm tasked with the design and construction of the two berm projects. Pending regulatory approval, watercourse re-alignment, bank stabilization and armouring construction is scheduled to commence in the spring of 2023.
January 11, 2023: Updated Flood Office Project Schedule
The updated schedule is now available for berm construction projects in Midland, Newcastle, Grove Plaza, Willow Estates, Downtown Drumheller, Michichi Creek West and East, Hospital, East Coulee, Rosedale and Nacmine. The schedule includes planned construction through to the end of 2024.
The schedule is subject to change based on the progress of property acquisitions, regulatory approvals and material supply.
At this time, funding has not been guaranteed for berms in West Rosedale, North Cambria, Rosedale Highway 10x and Riverwood Close. These projects will be re-assessed in the future.
To download the updated program schedule, click here.
January 9, 2023: House Relocation Sale (Coming Soon)
The Town of Drumheller will soon be advertising for interested parties to bid on homes that have been purchased as part of the Flood Mitigation program. The bid process will allow interested parties to purchase, salvage and relocate structures on any of the properties. Once moved, the lands will be cleaned up and returned to their natural conditions.
Advertising will be posted here and on the Drumheller Flood Mitigation website in mid-February. Bids will close at the end of March. More information on the properties, upcoming bidding process, dates, and process will be posted once details are finalized.
December 19, 2022: What We've Heard & How We're Responding Reports
The "What We've Heard & How We're Responding" reports from the November 17th Community Engagement Event have been uploaded to the Flood Website.
December 5, 2022: Tree & Shrub Procurement & Planting Award Summary
On December 5, 2022, the Tree & Shrub Procurement & Planting Tender was awarded to Wilco Contractors Southwest Inc in the amount of $1,287,163.00.
December 2, 2022: Berm Construction Paused for Winter Months
The Drumheller Resiliency & Flood Mitigation Office (Flood Office), in tandem with Wilco Contractors Southwest Inc and Pidherney’s Construction Inc, will be pausing construction of the Midland, Newcastle, Willow Estates, and Grove Plaza berms until the Spring of 2023.
November 21, 2022: Community Engagement Event Documentation
Following the Community Engagement Event for the Michichi Creek, Hospital Extension, East Coulee, and Downtown Berms on November 17, 2022, the Flood Office has uploaded all the documents shared at the event.
The DRFMO is proud to announce, on behalf of the Tree Carving Event Committee, that the video of the live carving is now complete.
To watch the incredible work of Marina Cole, and the impressive dinosaur bench she carved, CLICK HERE.
October 26, 2022: Newcastle Park Access During Construction - Update
The contractor working on the berm at Newcastle Beach Park has implemented a new no-parking zone along the East side of 10th Street West. This will allow the contractor to complete their work more safely, as their haul truck drivers have noted concerns about the visibility of children playing in between the vehicles. In the coming days, the haul trucks will also need to bring fill to the lot beside 10th Street West, so will need to have all vehicles moved from this area to allow for access. Local residents are encouraged to park on the West side of 10th Street West or at the Newcastle Park parking area located along 2nd Ave West near the blue A-frame building.
To view a map of the Newcastle Park access during berm construction, CLICK HERE.
October 19, 2022: Vibration Monitoring Update
The DRFMO has provided an update on the vibration monitoring that is taking place in construction areas.
October 7: Noise Relaxation for Willow Estates & North Drumheller Grove Plaza Berm Construction from October 8 - December 31, 2022
Please be advised that the Town of Drumheller has relaxed the Community Standards Bylaw 06-19 to allow for Wilco Contractors Southwest Inc. to conduct work on the Willow Estates and North Drumheller Grove Plaza Berm Construction projects.
This relaxation will apply to the following:
work may commence at 7:00 am on Saturdays & Sundays
work will cease at 10:00 pm on Saturdays & Sundays
this relaxation will end at 10:00 pm on December 31, 2022
Upcoming Community Engagement Session: East Coulee, Hospital, Michichi Creek, and Downtown Berm
The DRFMO cordially invites you to join us for an in-person Community Engagement Session at the Badlands Community Facility. The session will focus on the East Coulee, Hospital, Michichi Creek, and Downtown Berms.
Time: 6:00 PM - 8:00 PM Location:Badlands Community Facility.
October 1, 2022: Noise Relaxation for Midland Berm Construction from October 1 - December 31, 2022
Please be advised that the Town of Drumheller has relaxed the Community Standards Bylaw 06-19 to allow for Wilco Contractors Southwest Inc. to conduct work on the Midland Berm Construction project. The affected area is identified on the corresponding map.
This relaxation will apply to the following:
work may commence at 7:00 am on Saturdays & Sundays
work will cease at 10:00 pm on Saturdays & Sundays
this relaxation will end at 10:00 pm on December 31, 2022
October 1, 2022: Noise Relaxation for Newcastle Berm Construction from October 1 - December 31, 2022
Please be advised that the Town of Drumheller has relaxed the Community Standards Bylaw 06-19 to allow for Pidherney's Inc. to conduct work on the Newcastle Berm Construction project.
This relaxation will apply to the following:
work may commence at 7:00 am on Saturdays & Sundays
work will cease at 10:00 pm on Saturdays & Sundays
this relaxation will end at 10:00 pm on December 31, 2022
September 28: Tree Health Assessment Schedule - Fall 2022
Over the next few weeks, CCI will have biologists in the field conducting tree health assessments, which will be used to refine landscape plans in berm areas.
The tentative schedule is noted below:
Sep 29 – Oct 1 North Drumheller Michichi Creek West Berm
Oct 3 – 5 North Drumheller Michichi Creek East Berm
Oct 6 – 8 East Coulee Berm
Oct 10 Hospital Berm Extension
If you have questions or concerns, please contact the Drumheller Resiliency and Flood Mitigation Office. (403) 823-4878 floodreadiness@drumheller.ca
September 27, 2022: Special Ground-Breaking Ceremony Officially Signals Future Flood Mitigation Work
On September 27, 2022, the Town of Drumheller, along with representatives from the Federal and Provincial governments, announced during a special ground-breaking ceremony that construction of the Drumheller Flood Mitigation Project will begin later this fall.
September 23: Newcastle Berm Wildlife Sweep Report
Klohn Crippen Berger Ltd. (KCB) is pleased to provide a summary for the Newcastle Berm Wildlife Sweep conducted on September 19, 2022 to support the Town of Drumheller with respect to clearing vegetation for berm construction.
To view the report, click HERE. The report can also be found on the Resources page underneath the "Berm Construction" heading.
September 21: Midland Berm Wildlife Sweep Report
Klohn Crippen Berger Ltd. (KCB) is pleased to provide a summary for the Midland Berm Wildlife Sweep conducted on August 31, 2022 to support the Town of Drumheller with respect to clearing vegetation for berm construction.
To view the report, click HERE. The report can also be found on the Resources page underneath the "Berm Construction" heading.
September 21, 2022: Newcastle Park Access During Construction
A map of Newcastle Park that shows access during the construction period is uploaded to the Resources page on the flood website.
To view the Newcastle Park Access Map, CLICK HERE.
September 21, 2022: Willow Estates "What We've Heard & How We're Responding" Report
The Willow Estates "What We've Heard & How We're Responding" Report has been completed and uploaded to the flood website.
The report includes the following:
What We Heard
Q&As from the virtual Willow Estates Community Engagement Session on March 31, 2022
Q&As from the Willow Estates Berm Walk-Through on September 7, 2022
“Where Would You Like to See Vegetation Planted” survey results that pertain to the Willow Estates Berm Project
September 15: Drumheller Sagebrush to be Harvested by Calgary Zoo
Next week, Calgary Zoo staff and volunteers will be harvesting sagebrush from the Newcastle and Willow Estates berm areas in Drumheller. The sagebrush will be used as feed for the Zoo’s greater sage-grouse population in the coming year.
September 14, 2022: Willow Estates Wildlife Sweep Report
Wood Environment & Infrastructure Solutions Canada Limited (Wood) was retained by the Drumheller Resiliency and Flood Mitigation Office (Town of Drumheller) to undertake a pre-construction survey (wildlife sweep) in support of site clearing and development activities proposed to begin September 2022 along the Red Deer River, adjacent to the community of Willow Estates in Drumheller, Alberta.
To view the report, click HERE. The report can also be found on the Resources page underneath the "Berm Construction" heading.
September 13, 2022: Drumheller Resiliency & Flood Mitigation Program Schedule
The Drumheller Resiliency & Flood Mitigation Program Schedule has been updated. Please note that this schedule is subject to change.
September 7, 2022: Grove Plaza Berm Wildlife Sweep Report
CCI Inc. (CCI) was retained by Kerr Wood Leidal Associates (KWL) to conduct a pre-clearing wildlife sweep of the Grove Plaza Berm. Specifically, the area North of the Red Deer River and east of Highway 56 where tree clearing will take place.
To view the report, click HERE. The report can also be found on the Resources page underneath the "Berm Construction" heading.
August 31: Willow Estates Wildlife Sweep
Before the tree removal process begins in Willow Estates, biologists are scheduled to conduct a wildlife sweep this week.
In accordance with the Urban Tree Strategy, trees in good or fair health will be replaced at a 5:1 ratio - five trees planted for every one tree removed.
Upcoming Community Information & Engagement Sessions
Midland Berm Walk-Through Tuesday, Sep 6 - 7:00 PM - 8:00 PM Location: Meet at the Corner of 25 Street NW and North River Drive. To RSVP, please email floodreadiness@drumheller.ca by Sep 5.
Willow Estates Berm Walk-Through Wednesday, Sep 7 - 6:30 PM - 7:30 PM Location: Meet at the Corner of Riverside Drive East and 19th Street East. To RSVP, please email floodreadiness@drumheller.ca by Sep 6.
Newcastle Berm Walk-Through Tuesday, Sep 13 - 6:00 PM - 7:00 PM Location: Meet near the Newcastle Beach. To RSVP, please email floodreadiness@drumheller.ca by Sep 12.
Downtown Berm Community Engagement Session Tuesday, Sep 20 – multiple time slots available. Location: Badlands Community Facility Registration:https://bit.ly/3Aq1PO3
August 25, 2022: Midland Pathway Closure Notification
The pathway in Midland along the Red Deer River between the CN Rail bridge and North Dinosaur trail will be closed for approximately 16 weeks from Monday, August 29th 2022 until December 2022. The pathway is being closed to facilitate the Midland Berm upgrade as part of the Drumheller Resiliency & Flood Mitigation Project.
The Town of Drumheller is hosting a tree carving event!
While the Town of Drumheller makes every effort to avoid impacting trees, sometimes the nature of capital projects requires that some trees are removed to make space for project work. Some of the trees removed will be repurposed through a project initiated by a group of residents and Mayor Colberg.
Marina Cole (the carver), who is better known through her business name of Chainsaw Spirit, is from Irvine Alberta and her passion is to take old, downed trees and give them a second life by transforming them into works of art.
Her love and talent have made Marina into a sought-after artist who has participated in international competitions in Alaska, Australia, Montana, British Columbia, Saskatchewan, Quebec, and Alberta.
Cole has created must-see chainsaw carvings throughout the Medicine Hat area, Alberta and BC and has opened Chainsaw Spirit Gallery in Irvine where she not only sells her woodwork, but products from other local artisans.
We're excited to announce that this event is fully funded by Alberta Culture Days!
August 16, 2022: Request For Decision: Engineering Consultant Scope Changes for the Midland and Willow Estates Berm Construction Services
At the Council meeting on August 15th, 2022, the Drumheller Resiliency & Flood Mitigation Office made 2 Requests for Decision. Council adopted these motions, and the details are below.
Motion Adopted: Moves that the Midland Berm construction services be awarded to Klohn Crippen Berger through a scope change in the amount of $275,741.50 excluding G.S.T.
Motion Adopted: Moves that the Willow Estates Berm construction services be awarded to Wood Environment and Infrastructure Solutions Canada Ltd through a scope change in the amount of $360,990.00 excluding G.S.T.
The Drumheller Resiliency & Flood Mitigation Office has hired a local videographer to do aerial drone surveys every two weeks (for 4 months) of the berm project areas during construction. If you see a drone flying above, this is what it's for.
August 8: Traffic Impact Assessment - Downtown Dike and Riverside Drive - Traffic Volume Comparison
The Traffic Volume Comparison report for the Downtown Berm and Riverside Drive is now available on the Resources page on the Flood Readiness website, under the Riverside Drive heading.
This report, created by JCB Engineering, compares traffic volumes data recently collected by the Town of Drumheller along Riverside Drive / 5 Street between 3 Avenue and 4 Avenue to traffic volumes used in the Transportation Impact Assessment (TIA) completed by JCB on April 12, 2022.
August 2: Council Moves to Award Project Tenders for the Construction of The Newcastle, Midland, North Drumheller Grove Plaza, and Willow Estates Berms
Construction tenders have been awarded for the Newcastle, Midland, North Drumheller Grove Plaza, and Willow Estates berms.
TheTown of Drumheller is looking for interested parties to purchase and salvage three properties in Lehigh and two in Nacmine, which have been purchased as part of the Flood Mitigation Program.
July 12, 2022: "Where Would You Like To See Vegetation Planted In Drumheller" Survey
The DRFMO is focusing on the construction of 4 dikes in 2022 (Midland, Newcastle, Grove Plaza, and Willow Estates).
In order to prepare these areas for their respective dikes, some trees had to be removed.
As promised in the landscape plan, any trees in good or fair health will be replaced at a 5:1 ratio - 5 replacements for every 1 removal. These replacements may be trees or shrubs or a combination of trees and shrubs.
The intent of this survey is to gather community feedback on where residents would like to see the vegetation planted in Drumheller. Please note that replacements will be prioritized in the same community as where the trees were removed from.
This survey will close on Friday, September 2nd, 2022, so please provide your input before then!
July 4, 2022: Resiliency and Flood Mitigation Program Quarterly Report
On July 4, the Resiliency and Flood Mitigation Program’s Technical Advisor, Mark Steffler, P. Eng., presented a Quarterly Report to Mayor and Council. This report covers the period from April 1 to June 30, 2022.
The Town of Drumheller hereby gives notice that three (3) submissions have been added to the Navigable Waters Registry pursuant to the Canadian Navigable Waters Act for public comment described herein and its site and plans.
As part of the Drumheller Resiliency and Flood Mitigation Office’s commitment to transparency and keeping residents informed on project progress, the following update provided to Mayor and Council on Monday, June 6, 2022, is being shared with the public.
May 26, 2022: Traffic Count Raw Data - May Long Weekend - 5th Street Merged
Over the May Long Weekend, a traffic count was conducted by the Town of Drumheller along Riverside Drive / 5 Street between 3 Avenue and 4 Avenue from May 19 to May 24, 2022.
Traffic volumes were collected using an automated traffic recorder. The raw, provisional data is available on the Flood Readiness website's Resources page, under the Riverside Drive heading.